I knew it was a bad omen on Friday morning when there was no milk for my team, sitting down sans refreshment, the door opened and the Area Manager said, “ahh, just the man I was looking for”.
A wall in the nearby town of Arundel had collapsed at 3:30am, with 3 days of spring tides and heavy rain forecast the situation was less than ideal.
I mobilised a team of engineers and contractors on an emergency contract and we hastened to the site. The collapsed wall was behind a terrace of houses on a narrow road and completely inaccessible. The River Arun is the 2nd fastest flowing river in the country, the only vessel powerful enough to hold station in the flow and fit under the bridge was several hundred miles away. This limited our repair options somewhat.
The wall is a privately owned structure, however the Environment Agency and our responding partners are tasked with protecting all of the properties from flooding now the defence was breached. We made the decision to try to stabilise the current collapse and prevent further collapse and wider flood risk.
The plan formulated was to lower flexible bags of stone into the breach, protecting the remaining material from the full force of the flow and hopefully prevent further deterioration. This would take some doing, the nearest clear road is 25m horizontally away from the breach with 3 houses in the way.
At the same time we would isolate the terrace of houses with a temporary flood defence structure enabling us to contain flood waters that flowed through the breach and immediately pump them out.
Arundel is the very definition of English Market Town, every road is awkward, tight and cars occupy every spare piece of land. We made the call that into this we needed to bring a 120tonne crane, a low loader and four tipper trucks of material. Not easy.
An event of this size mobilises a huge variety of teams from Fire & Rescue, local authorities, Police and Highways. This team work was needed to close the roads and start the extremely difficult process of persuading locals to move their cars. Nothing is harder than breaking people’s need to park near their properties, fortunately a police uniform works wonders.
After a long and stressful day in the rain we finally positioned the crane at about 4pm on Saturday with 2 hours to low tide to get the operation started. A 120tonne crane builds itself with counterweights brought to site on a low loader. It cannot however work in winds over 7.5m/s, just as the 60m jib was raised a squall came in bringing hail and wind. A waiting game started.
As if we didn’t have enough to deal with the weight of the crane caused a failure in an old water main, in itself an extremely minor issue, however, the potential for washed out ground underneath a crane does not bear thinking about. We demobilised as hastily as possible (about 2hours for a crane that size) and retreated to lick our wounds and try again. (The high winds stayed all through the low tides halting work)
The next day we started again, the low loader could not be stored on site and had to complete the awkward half hour reverse back into position. In the meantime the utility company dug out the main repaired it and installed a new isolation valve to prevent a recurrence of the same risk. We also used a different method of loading the ground.
A 120tonne crane with a 60m jib in an urban environment is quite an arresting sight. The trucks of rock waited in a nearby services, we evacuated all adjacent properties and began. The four tonne flexible bags were craned over houses and lowered into the breach. This was done via radio as the crane driver was unsighted, all guidance was done from a boat. The rock was released by an operative on the bank once the engineer confirmed it was in position. All the site was under water and in the dark at this point.
The operation continued until 2am when we considered that immediate objective had been completed. We demobilised, switched the water back on and waited. We had no way of knowing if it had been a success until the next low tide.
It turns out the engineer on the boat must have had a wasted youth in arcades because the placement could not have been better
The stabilisation bags were placed before the next high tide which peaked some 20mm below the floor level of the property.
An extraordinary and emotional 3 days. I was absolutely shattered, physically and mentally. Every single person I dealt with from the emergency services, contractors, local authorities and utilities were prepared to work long hours in appalling conditions to try to protect the local properties and residents.
To complete an operation of this complexity within 3 days shows that despite the headlines we don’t do a bad job in this country.
James