Had some work done recently on a day rate + materials basis, which has worked pretty well previously with my builder. This time though the cost has come in nearly twice what I’d expected, so was hoping for a sense check before I query it with him. If anyone has the time, I’d be grateful for your thoughts on rates (Sheffield, if it matters).
2t digger hire, 2 days. £250?
Digger driver and labourer (digging) £200 + £120
Bricklayer and two labourers (mixing, carrying blocks) £250 + £120 + £120
Mini mix concrete, 2 cubic meters, poured direct (i.e. no carrying/pump) £350