My dad had the exact same problem with his small farm in 70s, they want as much back then to connect. He used a massive generator which ran off of a tractor PTO shaft, cheaper than stand alone generator clearly. This ran, an auger, small milking parlor, lights and any other tools he was using. Worth considering. He used this method for over 25 years as far as I'm aware, probably longer.
Hello
Sorry I haven't seen this thread earlier.
I understand your problems, but don't work for WPD (I'm Central Networks) but here are a few tips you could use when speaking to the planner/designer of your connection -
Firstly, is the connection near and existing TX/Power line or will it require a totally new build? this could influence things
All work bar the final connection can be done by anyone you like as long as it is inspected and approved for connection by WPD. This was brought in under the competition in connection regs. Doing the ground work yourself could save you money..
If you are getting WPD to do all the works make sure that the Maximum demand you have given them takes into account diversity factors (Known as ADMD - Maximum demand after diversity)
Just because your largest appliance uses 10KW, your usage, after diversity will be more like 3.5kW as long as the appliance is not run all the time (ie a house with a gas supply will be given a MDAD of 2kW even with a 9kX shower) - this will reduce the cost by getting a small section cable or Tx installed
The second option, but only available if there is existing infrastructure in the area, is to get WPD to do any upgrade work as asset improvement and hope that they just charge you just the basic additional work and not the entire cost.
Have a look at this tread - http://www.singletrackworld.com/forum/topic/anyone-from-eon-in-new-electricty-connections-highway-robbery
Another chap on here called IGM works for CE electric as a new connection manager. He has loads of other useful advice as seen in the thread above
Tom
Jumping_flea can you help, I see this is your line of work, please, please could you or any one tell me how long it takes these guys to fit a high voltage transformer to a pole and how long would it take to fit a new pole under high voltage cables and connect the wires? The labour comes to nearly half the cost, which seems very high to us.
Sorry - I misread some of the quote, I see you are doing some of the work yourself.
Central Networks normally gives time-scales of 12 weeks from payment to complete the work. However time onsite to install and wire a TX is 1 day to prep and 1 day to connect - cable to pole etc and LV wiring (Including local shutdown and giving residents notice of the interruption)
Any customer that will be affected by the outage needs a minimum of 5 working days notice before being switched off to connect your supply
what jumpin_flea says although there are companies that will negotiate with the upplier/installer on our behalf. They usually take a fee (typically 30%) of anything they save you.
Here is one example i found from google;
http://www.powermatters.com/
not used them myself but I have usd similar ones (some successful some not) and it might be worth exploring
Ask the utility for a full breakdown of the costs
Hi jumping_flea and Gooner,
Thanks so much for getting back to me.
I will try and answer your questions:
Firstly, is the connection near and existing TX/Power line or will it require a totally new build? this could influence things
Not sure what the term TX/power line is but the high power line with three cables crosses the corner of our field. The only pole on our ground is a T off pole where two cables go off the pole at 90 degrees to a local farm. WPD say they want to put another pole 2m to 3m away from that under the three cables to put the transformer on, this is very costly and to me doesn,t seem necessary. would Central Networks allow a 50 kva or kw 3 phase transformer on a T off pole and if so what are the clearances off the floor etc.
All work bar the final connection can be done by anyone you like as long as it is inspected and approved for connection by WPD. This was brought in under the competition in connection regs. Doing the ground work yourself could save you money..
We are doing a lot of the ground works already. Can we use another company besides WPD to say, put this pole in and fit the transformer and connect all except the final connection onto the high voltage cables.
The second option, but only available if there is existing infrastructure in the area, is to get WPD to do any upgrade work as asset improvement and hope that they just charge you just the basic additional work and not the entire cost.
Not quite sure what you mean by the above as power lines do cross our land but I didn't say that originally.
Central Networks normally gives time-scales of 12 weeks from payment to complete the work. However time onsite to install and wire a TX is 1 day to prep and 1 day to connect - cable to pole etc and LV wiring (Including local shutdown and giving residents notice of the interruption)
So would it take 4 man days. 2 men for 2 days or are the teams bigger than 2 men.
Do you think I can get them down on price, besides the pole, transformer and earthing there is 130m of cable to the meter point.
I hope this isn't going to be the actual cost as I don't know how we could afford it.
Any help would be very much appreciated.
wildgoatie - first some questions
What will the supply be feeding? Have you worked out your final load requirement in KVa? Is it going to be 3phase or single phase?
You mention it is 130m to your meter point, this will create a volt drop that will prop require you to install a 95 wavcon cable.
Depending on the construction of the t off pole, it would be possible to hang a tx on this pole - however without looking at it, clearances could be an issue, also a transformer creates extra loading on a pole a require a stout pole if the construction is not already suitable - this could be blagged to get WPD to pay for the upgrade and get them to treat it as betterment on their network - talk to the planner about this....
TBH, I have (along time ago) quoted similar prices for a new freestanding TX pole with transformer, cable terminations and the cost of the cable etc.
Are you digging the trench and WPD installing the cable? One option could be to install a meter cabinet close to the proposed transformer pole and install a private cable to your property. You would cut down the WPD cable costs, but you would then have to purchase a cable of sufficent cross section area to ensure you get a decent amount of volts at your property. (If a single ph connection is required this could be done by bunching a 3phase cable)
Hopefully some of this make sense or may help
Tom
EDIT
Not sure what the term TX/power line
TX = Transformer
Power line - HV or LV overhead line. You mention the line crossing your field has 3 wires - this is a 3phase 11kV line with a single phase t off to the farm.
Just to clear up the labour required -
- 1, 2 man team to install and wire a freestanding pole prior to the shutdown day
- 1 waggon to transport material to site
- JCB to excavate ground and install earthing for new TX
- Depending on how many customer are affected by the outage - 1 man to deliver outage cards informing customer they will be off supply while the work is done
- 1 jointing team for a couple of hours to terminate the cable if 95 wavecon, if 35mm CNE then the linesmen can do this
- 1 linesman team (including an authorised engineer) to switch off the HV and connect up the supply
##Additional costs could be incurred if WPD send a gang out to pull the LV cable into the trench you have dug##
