The National Audit Office, drew up a detailed baseline for controlling the budget.
A total of 8.1 billion pounds will be made available to the Olympic Delivery Authority, including 2 billion pounds of contingency.
A total 1.2 billion pounds will be spent on non-ODA activities, such as elite and community sports, the Paralympic Games and security.
Here is an outline of the costs in millions of pounds, including VAT, unless stated otherwise:
Non-ODA costs:
Elite and community sports, 290; Paralympic Games, 66; Look of London, 32; security, 600, and security contingency, 238.
ODA costs:
Site preparation and infrastructure total: 1.94 billion pounds.
This includes work on: power lines, 282; utilities, 255; enabling works, 364; structures such as bridges and roads, 830, and other infrastructure, including landscaping, 206.
Venues total: 1.2 billion pounds.
This includes: the main stadium, 496; other Olympic Park venues, 574, and non-Olympic Park venues, 101.
Transport: 897.
This includes: Stratford regional station, 119; contribution to DLR upgrade, 86, Thorntons Field relocation, 47; contribution to North London Line upgrade, 110; other transport capital projects, 178, and other transport operating expenditure, 357.
Other parkwide projects total: 868.
This includes: logistics for site construction, 337; section 106 and master planning, 127, and security for park construction, 354.
Other costs include:
The government is forecast to contribute 492 million pounds towards the cost of the broadcast and media centres and Olympic village.
The programme delivery, including provision for performance-related payments, 647, and corporation tax and net interest, 73.
The 500 million pounds contingency, which has already been given to the ODA, was broken down also.
It included (in millions of pounds): site preparation and infrastructure, 177; venues, 100; transport, 21; other parkwide projects, 208.
Source: Department of Culture, Meida and Sport.