I wouldnt pay up front for hardware.
Fair enough, I’m happy to admit I don’t have any experience with IT hardware procurement, so I’m not sure what current practice is there!
Thanx mogrim…so that’s 40 on order 40 at delivery and 20% when the delivered system is “working” as it should be ?
No, that’s 40% on delivery of the first (software) module – with a certain leeway on the bug front. 40% for the second module, and the remaining 20% when all bugs have been fixed and the system is ready for production.
In your case I’d be thinking 40% for delivery and installation of hardware, 40% for all data migration and systems, and 20% once training has taken place. Don’t forget to include some kind of (year long?) guarantee, I’ve also seen places hold back 5% for the first 3 months after going live to cover this.
(40/40/20 would depend on the values of what you’re asking for, if hardware is really only 20% of the project value you’ll want to change this of course!)